The Montour Trail

Montour Trail-Letter

The Official Publication of the Montour Trail Council

Access and Maps News of the Trail Membership and Volunteering Half Marathon Links
The Montour Trail > News and History > September/October, 2001 > Status of TEA 21 Project

Volume 12, Issue 5
September/October, 2001

Status of TEA 21 Project -- Phase I
(McDonald Trestle Bridge to Chartiers Creek)

by Dick Quasey

In early August the design drawings were approved and now the completion of all of the construction documents (drawings, specifications and contract conditions) is expected in mid-September. PADOT approval of these documents ought to be given by late October. Advertising for bids then could occur in early November and receipt of bids in mid-December.

With the award of a construction contract for Phase 1 in early January, construction should actually start in late February.


Last modified 10/17/01

For comments and questions:
about the trail: info@montourtrail.org
about the Half Marathon: race@montourtrail.org
about the website: webmaster@montourtrail.org


Hosted and sponsored by PghConnect