Montour Trail construction continues project
by project towards the ultimate goal of a continuous
46 mile long trail from Moon Township near Coraopolis to Clairton,
with several planned branches, including a connection
to the Pittsburgh Airport.
Today, about 40 miles of trail are completed; but completed miles are not all connected, being isolated by a few large uncompleted sections, as well as some missing bridges requiring at-grade crossings of public roads. The statuses of seven specific projects are summarized in the page below. Please bear in mind that forward-looking statements in these project descriptions are subject to change. The MTC continues the process of detailed planning, fund raising, volunteer construction, and oversight for each individual project. |
Volunteers Bill Capp, Andy Glaid, and Rich Blaskiewicz
applying a crushed-limestone top surface to a new trail section
in East Peters
|
|
| The Montour Panhandle Connector (mile 16.9) | ||
|
COMPLETED - SPRING 2007
The 1.0 mile connector was opened in late 2005 after renovation of the Robinson Run bridge, but the trail surface was unfinished. Project goals include ditching/drainage improvements, final grading/surfacing, and signage installation. The connector intersects the Montour Trail at mile 16.9 and intersects the Panhandle Trail about 0.4 mi west of the McDonald Trestle at Primrose. detailed connector directions Current Status: completed in spring 2007 More Details: Connector Project Page |
|
|
| Route 50/980 Crossing in Venice (mile 21.9) | ||
|
Starting from mile zero in Moon Township near Coraopolis, the first major gap in
the Montour Trail exists in Venice (trail mile 21.9) where
the trail crosses the intersection of routes 50 and 980.
Currently, trail users must use a 0.6 mi long bypass route Venice bypass route on public roads to get around this gap. A new Montour Trail bridge is planned to span over this intersection, but installation of a new bridge cannot proceed until PENNDOT makes planned improvements to the road intersection. Shorter term, a project utilizing an "at grade" crossing will be implemented; eliminating travel along the bypass route. However, trail users will still have to make the public road crossing at this busy road intersection. Funding for the short term project was generously provided by Mary Shaw and Roy Weil, authors of "Freewheeling Easy," the definitive guide to trails in and around western Pennsylvania. FreeWheeling Easy in Western Pennsylvania To volunteer for work on this project, contact Ned Williams at . Current Status: work on the temporary "at grade" crossing began in 2007 and is partially complete. View Project Photos Est. Completion: temporary crossing in Spring 2007, Montour Trail Bridge over intersection is 3-5 yrs in the future More Details: Venice Crossing Project Page |
![]() ![]() |
|
Morganza Road Bridge Project (mile 27.1, gap currently shown without bridge)
|
||
|
The gap at Morganza Road in Hendersonville is the second major gap in the Montour Trail (trail mile 27.1). The trail master plan specifies installation of a new bridge at this location allowing trail users to avoid crossing Morganza Road. Current Status:
Est. Completion: Late 2009 More Details: Morganza Crossing Project Page |
||
Georgetown Road Bridge Project (mile 27.3, gap currently shown without bridge)
|
||
|
This trail gap at Georgetown Road is located about 1/4 mile east of Hendersonville. Installation of a new bridge at this location is planned, and trail users will no longer have to cross this public road. Current Status:
Est. Completion: Late 2009 More Details: Georgetown Crossing Project Page |
||
| Greer Tunnel to Route 19 Project (miles 28.5 - 30.5) | ||
|
One of the larger trail projects involving grading and surfacing
two new miles of trail, installation of three new bridges, renovation
of two existing bridges, and renovation of the Greer Tunnel. When
completed, the two largest trail sections (Moon Township near Coraopolis to Hendersonville)
and (Peters/Arrowhead/Bethel Park) will be connected.
See the unfinished trail section
(represented by dots) on map to right. Current Status:
Est. Completion: Late 2008 for the 3 westernmost bridges and trail surface between these bridges. The 2 eastern bridges are 3 to 5 years away from construction. More Details: Cecil-Peters Project Page |
|
|
| Library Trestle Rehabilitation (mile 35.2) | ||
|
Expansion of the trail from Bethel Park-Library eastward will utilize the existing Library trestle.
Linking the Bethel-Library trail section with the existing 1.2 mi long trail section located
along Piney Fork road is an important goal of the trail council. Currently, the Piney Fork trail
section is completely isolated from other trail sections.
Currently, original railroad rails are mounted on the Trestle deck (shown in photo to right). This project will involve removing the existing rails and ties from the Trestle, making some structural improvements to the bridge, then installing a new deck/fencing. There are short sections of trail on either side of the bridge that will also be built. When finished, trail users will enjoy a spectacular view of the surrounding neighborhood from an elevated point. Current Status: Engineering work in progress; construction funding sources identified. Est. Completion: Late 2008 More Details: Library Trestle Project Page |
|
|
| Clifton Road Bridge (Bethel Park Branch) | ||
|
A gap in the Bethel Park Branch of the Montour Trail exists at Clifton Road. To get across busy
Clifton road, trail users currently must descend a walking path, carefully cross
the road, and then ascend a walking path on the opposite side.
Significant numbers of school children use the trail in this area to travel to/from George Washington Elementary school located less than a hundred yards from the trail (visible in upper left section of photo). A new Montour Trail bridge is planned to bridge this gap in the Trail Current Status: bridge design is in the final phase Est. Completion: late 2009 More Details: Clifton Road Bridge Page |
|
|
|